The History of Chiryurtskaya Hydropower Plant Construction

fabiano 0 2623  
 
dagestanhydropowerplantphotos-16.jpg
 
On December, 22nd, Chiryurtskaya Hydropower Plant-1 on the Sulak River is turning 50. In this article, we want to tell you about it, show some file footages and museum exhibits showing organization of the plant.
Soviet scientists have always known about Dagestan’ potential in water power (mostly due to its Sulak River) and began building first hydropower plans before WWII. When the war began, they had to freeze construction works and were able to resume it only in 1948.
Modern Chiryurtskaya Hydropower Complex consists of three power stations: Chiryurtskaya Hydropower Plant-1 and 2 and Gelbakhskaya Hydropower Plant-3.

dagestanhydropowerplantphotos-17.jpg
 

The water reservoir has three purposes: power production, irrigation and water supply. It has a length of 10 km, width of 0.82 km and depth of 12 m.

That dark blue building is Gelbakhskaya Hydropower Plant, it was built in 2006.


dagestanhydropowerplantphotos-18.jpg
 
The diversion canal is 3460 m long, 7 m wide and 8.8 m deep.

dagestanhydropowerplantphotos-19.jpg

dagestanhydropowerplantphotos-20.jpg

dagestanhydropowerplantphotos-21.jpg
 
A larger model of the plant can be found in the museum of RusHydro in Dagestan.

dagestanhydropowerplantphotos-22.jpg
 
dagestanhydropowerplantphotos-23.jpg
 
Preparatory works began in 1954 when they prepared construction sites, built power lines, houses for workers, storages
and other facilities. In 1955, they began excavating and by 1956, they built the first coffer dam.

dagestanhydropowerplantphotos-24.jpg

dagestanhydropowerplantphotos-25.jpg
 
The underwater construction of one of the power stations completed in 1957.

dagestanhydropowerplantphotos-26.jpg

dagestanhydropowerplantphotos-27.jpg

dagestanhydropowerplantphotos-28.jpg

dagestanhydropowerplantphotos-29.jpg

dagestanhydropowerplantphotos-30.jpg

dagestanhydropowerplantphotos-31.jpg

dagestanhydropowerplantphotos-32.jpg

dagestanhydropowerplantphotos-33.jpg
 
After they completed main facilities construction, they started building the canal head
and the body of the dam and the work’d lasted since 1958 till 1961.

dagestanhydropowerplantphotos-34.jpg

dagestanhydropowerplantphotos-35.jpg

dagestanhydropowerplantphotos-36.jpg

dagestanhydropowerplantphotos-37.jpg

dagestanhydropowerplantphotos-38.jpg

dagestanhydropowerplantphotos-39.jpg

dagestanhydropowerplantphotos-40.jpg

dagestanhydropowerplantphotos-41.jpg

dagestanhydropowerplantphotos-42.jpg

dagestanhydropowerplantphotos-43.jpg

dagestanhydropowerplantphotos-44.jpg

 

dagestanhydropowerplantphotos-45.jpg
 
‘Keep your hands off Lebanon’.
The point was that the president of Lebanon asked the USA to help him preserve power over the country which was on the verge of a civil war. Thus, American troops remained in the country for several months which caused discontent among Soviet people.

 

dagestanhydropowerplantphotos-46.jpg

 

dagestanhydropowerplantphotos-47.jpg

 

dagestanhydropowerplantphotos-48.jpg
 
22 December, 1961, Chiryurtskaya HPP-1 was put into operation.

 

dagestanhydropowerplantphotos-49.jpg

 

0 Comments
Category
State
  • 현재 접속자 59 명
  • 오늘 방문자 32 명
  • 어제 방문자 2,125 명
  • 최대 방문자 14,296 명
  • 전체 방문자 1,325,267 명
  • 전체 게시물 10,948 개
  • 전체 댓글수 35,460 개
  • 전체 회원수 71 명
Facebook Twitter GooglePlus KakaoStory NaverBand